ModelRisk example · Oil and gas
Chance of Success with Shared Risk
One well, two stacked targets that share the same source rock. What are the real chances of success, and what is the well worth?
From the model’s saved run
Chance of success
Analytical with the charge shared, analytical as if independent, and simulated.
| Chance of | Unit | Shared | Independent | Simulated |
|---|---|---|---|---|
| Oil in the Upper target | probability | 42.0% | 42.0% | 40.8% |
| Oil in the Lower target | probability | 27.3% | 27.3% | 26.9% |
| Oil in at least one target | probability | 52.9% | 57.8% | 52.3% |
| Oil in both targets | probability | 16.4% | 11.5% | 15.4% |
S-curve (cumulative probability) of Value of drilling the well from the saved simulation.
The business question
The Harrier exploration well will test two stacked sandstone targets, Upper and Lower. Both need oil to have been generated and to have migrated into the structure — a single shared risk. Each target also needs its own reservoir and its own trap and seal, which are independent of the other target's.
A common mistake is to multiply each target's overall chance and treat the two targets as independent. Because the charge risk is shared, that overstates the chance of finding oil in at least one target and understates the chance of finding it in both. The model shows the difference, then values the well using the risked discovered volume.
- Who it is for
- Prospect evaluators, exploration managers and anyone combining chance factors for several targets or prospects.
- Main outputs
- Chance of success per target, of at least one discovery and of both · outcome probabilities · risked volume · expected value of the well.
How the model works
Three sheets after this one, read from left to right. Each one feeds the next.
Inputs sheet
Chance factors are probabilities; success volumes are Lognormal from P90 and P10 estimates; well cost and value per barrel are PERT ranges.
Outcomes sheet
The chances are first combined analytically — once correctly, with the charge risk shared, and once as if the two targets were independent. Then one well is simulated: a Bernoulli trial for the shared charge and one for each target's own elements. A target succeeds only if the charge works and its own elements are present.
Results sheet
The simulation confirms the shared-risk numbers. The value of drilling is the discovered volume times the value per barrel, minus the well cost. Its mean over all samples is the expected value.
ModelRisk techniques
Find similar models
- Product
- Type
- Application
- Uses
The results in detail
Outcomes of drilling the well
Simulated share of wells ending in each outcome.
| Outcome | Probability |
|---|---|
| Dry hole | 47.7% |
| Upper target only | 25.4% |
| Lower target only | 11.5% |
| Both targets | 15.4% |
| Total | 100.0% |
Value of drilling
Expected value = the average value over all simulated wells, dry holes included.
Probability of at least each value of Chance of at least this volume from the saved simulation.
| Measure | Unit | Value |
|---|---|---|
| Expected value of drilling the well | US$m | 53.8 |
| Value of drilling, 90th percentile | US$m | 225.7 |
| Risked volume (dry holes count as zero) | MMbbl | 17.7 |
| Chance of a discovery | probability | 52.3% |
| Mean volume if oil is found | MMbbl | 33.8 |
| Chance of a dry hole (1 − chance of a discovery) | probability | 47.7% |
| Chance the well loses money | probability | 50.2% |
| Break-even size (mean cost ÷ mean value per barrel) | MMbbl | 7.2 |
| Recommendation | Drill: positive expected value |
How to read these results
- The charge is shared, so if it fails both targets are dry together. Treating the targets as independent counts the charge risk twice for 'both' and lets one target succeed while the other's charge fails — which cannot happen.
- So the independent shortcut overstates the chance of at least one discovery and understates the chance of both. The simulated column matches the shared-charge column, not the independent one.
- The expected value counts every outcome, including the dry holes. The 'mean volume if oil is found' is the risked volume divided by the chance of a discovery.
- The well loses money more often than it is dry: a discovery smaller than the break-even size — the well's cost ÷ the value per barrel, about 7 MMbbl — does not pay for the well either.
- The discovered-volume chart drops straight down at zero: the size of that drop is the chance of a dry hole.
See it move. Open the workbook, change an input on the Inputs sheet and run the simulation: every table and chart on this page updates in Excel.
Inputs and assumptions
Every assumption in the model, with its uncertainty and where it comes from. The figures are illustrative.
Shared chance factor 1 input
Applies to both targets at once: if the charge fails, neither target can hold oil.
| Assumption | Unit | Value |
|---|---|---|
| Source rock and chargeOil-prone source rock is proven nearby; the doubt is whether oil migrated into the Harrier structure. | probability | 70% |
Upper target 3 inputs
Target-specific elements, independent of the Lower target.
| Assumption | Unit | Uncertainty | Low | Most likely | High |
|---|---|---|---|---|---|
| Reservoir presence and qualityChannel sands seen on seismic. | probability | Fixed | 80% | ||
| Trap and sealDip closure under a thin shale. | probability | Fixed | 75% | ||
| Recoverable volume if successfulVolumetric range for the Upper target. | MMbbl | Lognormal · P90, P10 | 8.0 | – | 40.0 |
Lower target 3 inputs
Target-specific elements, independent of the Upper target.
| Assumption | Unit | Uncertainty | Low | Most likely | High |
|---|---|---|---|---|---|
| Reservoir presence and qualityDeeper sands; porosity may be degraded. | probability | Fixed | 60% | ||
| Trap and sealFault-bounded closure; seal along the fault is uncertain. | probability | Fixed | 65% | ||
| Recoverable volume if successfulVolumetric range for the Lower target. | MMbbl | Lognormal · P90, P10 | 12.0 | – | 60.0 |
Economics 2 inputs
Cost of the well and the value of each barrel discovered (US$, real terms).
| Assumption | Unit | Uncertainty | Low | Most likely | High |
|---|---|---|---|---|---|
| Exploration well costDeeper well to reach both targets; spent whatever the result. | US$m | PERT | 30.0 | 36.0 | 50.0 |
| Value per barrel discoveredDevelopment NPV per barrel from screening economics of similar discoveries. | US$/bbl | PERT | 3.00 | 5.00 | 8.00 |
Units and conventions
- Chance factors
- Probabilities that an element is present. A target succeeds only if every element it needs is present.
- Volumes
- Recoverable oil if the target succeeds, in million barrels (MMbbl); P90 is the low estimate, P10 the high.
- Value
- US$ million; value per barrel is the development NPV per barrel of discovered oil.
Key assumptions and limitations
- Dependence
- Only the charge is shared. In practice trap and seal can be partly shared too; add another shared Bernoulli for that.
- Value
- A constant value per barrel; development economics of each discovery size are not modelled (see OG-05).
- Volumes
- The two targets' volumes are independent of each other.
- Data
- All figures are illustrative. Harrier is not a real prospect.
How to use it
- Change the chance factors, volumes and costs on the Inputs sheet.
- Press F9 and watch the Outcomes sheet: each recalculation is one possible result of drilling Harrier.
- Run a simulation from the ModelRisk ribbon (10,000 samples with a fixed seed are set).
- Compare the three columns of the chance-of-success table on the Results sheet.
ModelRisk functions used
- VoseBernoulli
- Whether the shared charge works and whether each target's own elements are present.
- VoseLognormalAlt
- Success volumes from P90 and P10 estimates.
- VosePERT
- Well cost and value per barrel.
- VoseInput, VoseOutput
- Name the uncertain inputs and the outputs.
- VoseSimMean, VoseSimProbability, VoseSimPercentile
- Simulation statistics on the Results sheet.
Further reading
- Monte Carlo simulation explained (Vose guide)
- Rose, P. R. (2001). Risk Analysis and Management of Petroleum Exploration Ventures. AAPG Methods in Exploration 12.
- Vose, D. (2008). Risk Analysis: A Quantitative Guide, 3rd edition. Wiley — chapters on correlation and dependency.
- OG-06 extends shared risk to a portfolio of prospects in two plays.
Download the workbook and run it yourself. It opens in Excel with ModelRisk. The free trial runs every example model.
Related example models
- ModelRisk★★★★★Exploration Portfolio with Shared Play RiskWhich wells should we drill next year?Compares drilling programmes built from eight prospects whose success depends on shared play risk.
- ModelRisk★★★★★Exploration Prospect EconomicsShould we drill the exploration well?Several sheets, correlated inputs, a risk event, a stochastic price path and a 30-year cash flow.
- ModelRisk★★★★★Field Development Concept SelectionTieback, FPSO, or start small and expand?Three 25-year development cash-flow models on common random numbers, with a decision rule inside the simulation.
An illustrative example: the figures are invented for teaching and do not describe a real company, project or asset. Last updated 9 October 2026.