The Top 6 Project Risk Analysis Tools in 2024

6 Best Project Risk Analysis Tools

Summary of key review points

Product reviewed What you may like What you may not like Cost over 3 years ( )
Acumen Risk Simple interfaces
Single risk to multiple impact is realistic
Manages the correlation problem
Limited options for describing risk, especially no range for risk impacts
Price
~14,300
Primavera Risk Analysis (PRA) Nostalgia Not updated in 10+ years
Price
Very complicated interfaces
~10,800
Schedule Risk Analysis Runs in Excel, so lots of options for bespoke modelling Slow
Excel not ideal for networks
Price
~13,100
Risky Project Inexpensive
Feature rich
Overly complex interfaces
Aesthetics
~1,300 + maintenance
Safran Risk Very similar to PRA, but faster Limited options for describing risk
Poor handling of correlation
Price
~14,000 + maintenance
Tamara Fastest
Price
Largest options for describing risk
Handles the correlation problem
No ability to build schedule from scratch or edit links ~5,900

Acumen Risk

~ $14,300/3 years


What you may like:

  • Simple interfaces
  • Single risk to multiple impact is realistic
  • Manages the correlation problem

What you may NOT like:

  • Limited options for describing risk, especially no range for risk impacts
  • Price

Primavera Risk Analysis (PRA)

~ $10,800/3 years


What you may like:

  • Nostalgia

What you may NOT like:

  • Not updated in 10+ years
  • Price
  • Very complicated interfaces

Schedule Risk Analysis

~ $13,100/3 years


What you may like:

  • Runs in Excel, so lots of options for bespoke modelling

What you may NOT like:

  • Slow
  • Excel not ideal for networks
  • Price

Risky Project

~ $13,300/3 years
+ maintenance


What you may like:

  • Inexpensive
  • Feature rich

What you may NOT like:

  • Overly complex interfaces
  • Aesthetics

Safran Risk

~ $14,000/3 years
+ maintenance


What you may like:

  • Very similar to PRA, but faster

What you may NOT like:

  • Limited options for describing risk
  • Poor handling of correlation
  • Price
Best Price

Tamara

~ $5,900/3 years


What you may like:

  • Fastest
  • Price
  • Largest options for describing risk
  • Handles the correlation problem

What you may NOT like:

  • No ability to build schedule from scratch or edit links

Our Recommendation

For those with a very limited budget, RiskyProject provides good value for money. In contrast, ScheduleRiskAnalysis offers poor value from a project risk perspective, as it is only one part of a larger tool suite. Additionally, Primavera Risk Analysis is no longer actively developed or supported, which may pose challenges for IT compliance and long-term usability.

If you have more flexibility in your budget, it’s worth exploring the details of this article. Acumen Risk, Safran Risk, and Tamara are all robust tools, and the best choice depends on the nature of your projects and associated risks. Feature-wise, Tamara is priced lower than the others despite offering similar capabilities. To navigate directly to specific sections, use the links below:

Our Approach to This Review

Transparency is important—Tamara, the last software listed in the comparison table, is developed by our company. While we've made every effort to keep this review objective, we encourage you to critically evaluate our analysis.

This review starts by outlining why conducting a project cost and schedule risk analysis is essential. The key reasons are:

  • Without it, project cost and timeline estimates are likely to be unrealistic.
  • It helps identify opportunities to complete the project faster, at lower cost, and with greater predictability.

We then explore the key practical challenges in building a high-quality project risk analysis. Some of these challenges may be highly relevant to your projects, while others may not apply. Understanding how each software solution addresses these challenges should help you determine which tools warrant a closer look.

Unlike our review of Excel risk analysis add-ins, where we tested each product hands-on, this review is based primarily on available documentation and video materials, as downloadable trials for many of these tools are not readily available. To maintain fairness, we have summarized findings from these sources and determined whether there was enough information to assess how well each product addresses critical risk analysis requirements.

Pricing was also challenging to obtain. Before making a decision, we recommend requesting a detailed quote from vendors, covering the total cost of ownership for three years, including maintenance and updates.

While software aesthetics can be a consideration, our primary focus is on functionality. Some tools may not have the most polished interface but offer robust features. Ultimately, the most important factors are whether the software enables effective risk analysis for your needs and whether it facilitates, rather than complicates, the modelling process.

Why Project Risk Analysis is Essential

Project scheduling tools like Primavera and Microsoft Project are invaluable for planning and tracking project execution. They enable you to:

  • Define the tasks required to complete a project
  • Allocate resources for each task
  • Establish task dependencies and sequencing
  • Communicate execution plans with stakeholders
  • Monitor project progress

While these tools excel at project management, they fall short in forecasting realistic costs and timelines. This is where a dedicated project risk analysis tool becomes essential.

Reason 1: Achieving Realistic Delivery Goals

When start and finish dates are assigned to tasks in a scheduling tool, milestone and completion estimates are generated. Similarly, adding resource rates and expenses produces a total cost estimate. Many organizations rely on these estimates to set deadlines and budgets—yet they are often overly optimistic and, in many cases, highly unrealistic.

This inaccuracy arises because traditional scheduling tools do not account for uncertainty or risk events, both of which increase the likelihood of cost overruns and delays. Risks are straightforward to grasp; for example, the risk of a rejected planning application may require resubmission, leading to additional costs and time. Such contingencies are rarely built into standard project schedules.

Uncertainty, however, is more nuanced. Consider a construction project where foundation excavation is required. If weather conditions are ideal, the task may take as little as 30 days. Under typical conditions, 35 days may be required, while extreme weather could extend it to 50 days or more. A probability distribution effectively captures this variability:

Example of how a triangular probability distribution is used to describe uncertainty

The blue curve represents the likelihood of different completion times. The probability is zero below 30 days and above 50 days, with the most probable estimate at 35 days. The distribution is skewed, with a longer right tail—reflecting the reality that while tasks can occasionally be completed slightly faster than expected, delays can be significantly longer. Statistically, when a probability distribution is skewed to the right, the probability of completing the task by the most likely estimate is always less than 50%. In this case, the chance is just 25%, and the true 50:50 estimate is around 38 days:

How a three point distribution corrects for the optimism bias of a best guess estimate

This demonstrates why using the most likely cost and duration estimates results in systematically underestimated budgets and timelines. If a project schedule is built using optimistic "best guesses," delays and cost overruns become inevitable—even when no major issues occur.

In summary, while scheduling tools are excellent for structuring and managing projects, they should not be relied upon for setting budgets and deadlines. Project risk analysis tools provide more realistic forecasts by accounting for uncertainty and risk.

Reason 2: Reducing Costs, Saving Time, and Increasing Predictability

Reducing project costs and accelerating completion are common goals. Project risk analysis tools identify which activities have the greatest impact on total cost and duration, as well as those contributing most to uncertainty.

In the planning phase, this insight allows teams to explore alternative execution strategies and select the most efficient approach. During execution, as tasks are completed and risks evolve, the analysis can be continuously refined—enabling better decision-making and more predictable outcomes.

Key Principles for Effective Project Risk Analysis

Conducting a project risk analysis is essential for making informed decisions and ensuring project success. However, an inaccurate or poorly executed risk analysis can be more harmful than having none at all—it may lead to committing resources to high-risk projects or dismissing viable opportunities. This section highlights common pitfalls in project risk modelling and explains how different tools address these challenges, helping you choose the right solution for your needs.

Managing Large Project Schedules

Complex projects often involve extensive schedules with thousands of tasks. Typically, immediate tasks contain a high level of detail, while long-term activities are more broadly defined. As the project progresses, completed tasks are replaced with more granular breakdowns of upcoming work. Risk analysis for such projects relies on Monte Carlo simulation, a computationally intensive process that requires substantial memory and processing power. Historically, running simulations on large schedules posed challenges due to software limitations, forcing teams to maintain a simplified secondary schedule for risk analysis. However, as schedules grow in complexity, maintaining two separate versions becomes impractical and highly time-consuming.

Breaking a large task into smaller sub-tasks presents additional challenges in risk analysis. For example, consider a fencing project originally estimated to take Triangle(30,40,60) days. As the project nears execution, the task is divided into ten equal sections, each estimated at Triangle(3,4,6) days. This segmentation can create an unintended effect—suddenly, the total projected completion time appears significantly shorter in the risk model than in the original estimate.

Uncertainty contraction effect as a result of breaking a task down into several parts

The underlying issue is that many risk analysis tools treat each task as statistically independent. This means that if one section of the fence takes longer than expected (e.g., 6 days), the model does not account for whether subsequent sections will also be delayed. The Law of Large Numbers (LLN) explains that treating tasks as independent reduces overall uncertainty in the model, often leading to misleadingly optimistic results. Software solutions address this challenge in different ways: (1) some ignore the issue entirely, (2) others apply a simulation technique that enforces 100% correlation among related tasks, and (3) the most advanced tools identify the root cause of uncertainty, ensuring task durations depend on a shared influencing factor.

Another key consideration is the practicality of assigning uncertainty manually across thousands of tasks. A more efficient approach is bulk uncertainty assignment—selecting a group of tasks and applying a global percentage variation. However, caution is needed: if uncertainty is influenced by a common factor, such as contractor efficiency, failing to model this correctly will again lead to an underestimation of risk due to the LLN effect.

Conclusion: For large-scale project simulations, ensure the chosen risk analysis software can handle complex schedules efficiently, supports high-speed processing, properly accounts for statistical dependencies, and offers bulk uncertainty assignment to streamline the process.

Describing uncertainty

Probability distributions play a crucial role in quantifying uncertainty in project risk analysis, particularly for task durations and cost estimates. Selecting the appropriate distribution is essential for accurately modelling variability and ensuring realistic projections. Below are some of the most commonly used probability distributions in risk analysis:

Probability distributions typically used for describing task duration and cost uncertainty in a project

  • Uniform – because it is so crude
  • Split Triangle – because it doesn’t match what people want to say
  • Normal– because the mean and standard deviation inputs are unintuitive, and life is not symmetric
  • Lognormal – same mean, standard deviation issues, and the tail can be wildly uncontrolled

  • Triangle – because people understand it, even if its crude, but it tends to overestimate uncertainty
  • PERT – a curvy Triangle, easy to understand, but it tends to underestimate uncertainty

  • Modified PERT –Last parameter alters how flat the curve is, controlling over/underestimation of uncertainty. I invented it, so a bit biased
  • ThreePoint – a Modified PERT where you give a “practical max”(like a 95th percentile) instead of the absolute max which is very hard to elicit from an SME. It’s a distribution specific to VOSE software products, so perhaps a bit biased here

Conclusion: Ensure the software includes at least one of the well-suited probability distributions, while avoiding those that may lead to inaccurate risk estimations.

Single Risk Event with Multiple Consequences

Some risk events can trigger multiple consequences. For instance, if a key supplier goes out of business, it could lead to delays in procuring multiple materials, increased costs, and operational disruptions. These impacts either occur together or not at all. If a risk analysis model does not properly account for such dependencies, it may significantly underestimate the overall risk exposure and the importance of mitigation strategies.

Conclusion: Choose risk analysis software that allows linking a single risk event to multiple potential consequences, ensuring a more accurate assessment of project vulnerabilities.

Modelling Risk Event Frequency

Risk events such as strikes, equipment failures, and accidents can occur sporadically, introducing delays and additional costs. Some risks, like the complete destruction of a building, can only happen once, while others may repeat over time. The probability of a one-time event is typically expressed as a likelihood, whereas recurring risks are better represented using an expected frequency (e.g., 0.7 occurrences per year). If a risk analysis tool does not differentiate between these two types, it may lead to inaccurate uncertainty estimates and ineffective risk mitigation strategies.

Conclusion: Ensure that the software can properly distinguish between single-event probabilities and recurring risk frequencies to enhance the accuracy of your risk model.

Impact of Adverse Weather

Weather conditions can significantly affect project timelines, particularly in industries reliant on outdoor work, such as construction, offshore operations, and infrastructure development. Extreme weather events, seasonal variations, and climate-related disruptions must be factored into risk models to ensure realistic scheduling and budgeting.

Conclusion: If weather variability is a critical factor in your projects, choose software that incorporates weather calendars or similar mechanisms to account for these uncertainties.

Managing Complex Cost Structures

Project schedules typically incorporate various cost elements, such as:

  • Fixed costs assigned at different project stages (start, mid, or completion)
  • Resource-based costs (e.g., hourly rates for workers, daily charges for equipment), linked to task durations
  • Overhead costs (e.g., office rentals), independent of specific tasks

Risk analysis software integrates these costs, applies uncertainty, and considers risk-driven cost variations to provide a realistic project cost estimate. However, many additional expenses, such as legal fees, materials, insurance, and financing costs, often fall outside scheduling tools. These are typically assessed separately by cost engineers and financial analysts, requiring integration for a complete financial overview.

Conclusion: If understanding total project cost uncertainty is critical, ensure the software supports data export for external analysis or includes a built-in financial simulation tool.

Evaluating Investment Risks

Projects are typically undertaken with financial returns in mind, whether it's launching a new product or constructing infrastructure for revenue generation. Investment risk analysis relies on discounted cash flow (DCF) modelling to assess financial viability, using metrics like net present value (NPV) and internal rate of return (IRR). Project delays can significantly impact financial performance—additional costs lower NPV, while delayed revenues further reduce profitability.

These calculations are often performed in Excel, with risk analysis tools like ModelRisk enhancing precision. Given that investment success depends on factors like discount rates (typically 10-15%) and IRR thresholds (e.g., 20-25% for strong projects, 5% for marginal ones), integrating project cost and schedule uncertainty into financial models is essential.

Conclusion: If investment evaluation is part of your project decision-making, choose software that can seamlessly export risk-adjusted cost profiles or, ideally, include financial modelling capabilities.

Ensuring Schedule Suitability for Risk Analysis

Effective project risk analysis requires a schedule structure that reflects realistic uncertainties. Fixed milestones and rigid task dependencies (e.g., forcing Task B to start exactly 30 days before Task A finishes) can conflict with probabilistic modelling. Similarly, assumptions that two tasks will finish simultaneously (Finish-Finish dependencies) may oversimplify actual project risks.

Conclusion: Planners should prioritize Finish-Start dependencies and avoid locked milestones to allow realistic risk modelling. Additionally, project risk analysis tools should perform logic checks to identify potential scheduling inconsistencies.

Considering Spreadsheet-Based Risk Modelling

For simpler projects, a full-fledged scheduling tool may not be necessary. In some cases, a well-structured spreadsheet model can effectively capture key risks and uncertainties. To explore practical examples, you can download and experiment with models such as this one and this alternative.

Project risk analysis software comparison table

Depending on your circumstances, in my view the lines in bold are the most important in differentiating between the products.

Product name Acumen Risk Primavera Risk Analysis Schedule Risk Analysis Risky Project Pro Safran Risk Tamara
Publisher Deltek Oracle Lumivero Intaver Safran Vose

Cumulative cost (USD - see reference):

1 year 10 300 10 800 4 355 1 200 14 000 2 140
2 years 12 300 10 800 8 710 ? ? 4 100
3 years 14 300 10 800 13 065 ? ? 5 900

Schedule-related features

Imports from (1): PV, MSP, OP PV, MSP PV, MSP PV, MSP PV, MSP PV, MSP
Performs update against master schedule Unsure Unsure Unsure
Performs schedule quality check Partial Partial
Imports cost data Partial
Edit schedule tasks and links
Create schedule from scratch
Runs very large schedules Unsure
Simulation speed (educated guess) Fast Slow Very slow Medium Fast Very Fast

Risk information input

Uncertainty in task duration as %
Uncertainty in task duration in units
Uncertainty in scope as %
Uncertainty in scope in units
Uncertainty in cost item as %
Uncertainty in cost item in units
Uncertainty of risk impact size
Uncertainty in productivity rates
Group uncertainty factors
Resource cost uncertainty Unsure
Work type aggregate factors
Unplanned work risk events Manual
Task-specific risk events Manual
Calendar delay risk
Weather calendar Manual
Link to external risk register Import Import (Pelican)

Scenario analysis options

Switch risks on/off Manual
Define multiple scenarios
Risk treatment analysis

Analysis and reporting

Results for any task or milestone With rerun
Compare different scenarios on 1 plot
Tornado charts for sensitivity Partly
Tornado charts use natural numbers [2]
Critical index
Total cost-Finish date joint plot
Cost profile over time
Stochastic Gantt chart
Report templates
Export formats PV, MSP, OP PV, PV,

Mathematical basis

Distributions [3] N, T, U MP, P, T, U L, P, T, U, + L, N, P, T, U, + P, T, U Any
Repeatable risk event supported Manual
Simulation spreadsheets built-in
One risk maps to multiple impacts Manual
IF THEN conditional modelling Manual Manual
Avoids correlation coefficients Manual

Footnotes

  1. PV = Primavera, MSP = Microsoft Project, OP = Open Plan
  2. Natural numbers means in units of currency or time, not a rank order correlation which is unintuitive
  3. L = Lognormal, MP = Modified PERT, N = Normal, P = PERT, T = Triangle, U = Uniform

Screen caps