From the model’s saved run

Which strategy?

NPV (US$m) on the business-case demand and over the simulated futures.

StrategyBusiness caseMean simulated10th pct90th pctChance of a loss
Build big now63.716.1−55.074.336.4%
Build small, stay small28.420.40.228.49.9%
Build small, decide later28.424.5−5.858.113.3%
NPV of each strategy — cumulative probability

The business question

A manufacturer is entering a new market where demand is about 100,000 units a year, growing about 3% a year but very uncertain. It can build a plant for 120,000 units now for US$90 million, or a 60,000-unit plant for US$55 million.

The small plant can be doubled at the start of year 3 for US$40 million, once two years of sales have shown whether demand is strong. If demand collapses, it can be sold for US$35 million instead. On the expected demand, the large plant has much the higher NPV, and the business case recommends it.

But the large plant's capacity is only valuable if demand grows, and its cost is sunk if it does not. The model simulates ten years of demand and values the three strategies on the same paths, with the decision rule of the staged strategy applied in every iteration.

Who it is for
Strategy and corporate development teams, capital allocation committees, project sponsors.
Main outputs
NPV of each strategy: the business case against the simulation, its range and the chance of a loss · the value of the options to expand and abandon · how often each decision is taken · the range of demand.

How the model works

Three sheets after this one, read from left to right. Each one feeds the next.

  1. Inputs sheet

    Today's demand, its growth and volatility; contribution per unit; each plant's capacity, cost and fixed costs. The expansion cost and the sale value; the demand levels at which to expand or to sell; the discount rate.

  2. Strategies sheet

    VoseTimeGBM draws ten years of demand. Each strategy sells what demand and its capacity allow. The staged strategy looks at year-2 demand: above the expansion level it doubles capacity from year 3, below the abandonment level it sells the plant at the end of year 2, otherwise it carries on.

  3. Results sheet

    Each strategy's NPV on the business-case demand and in the simulation, its range and chance of a loss; the value of the options; how often the plant is expanded or sold.

ModelRisk techniques

  • Demand as GBM VoseTimeGBM
  • Common random numbers
  • Real-option decision rules
  • NPV S-curves, demand fan chart

Find similar models

Product

The results in detail

The value of flexibility

What the options to expand and to sell add, and how often they are used.

Demand by year — 10th to 90th percentile
MeasureUnitValue
Mean NPV, build small and decide laterUS$m24.5
Mean NPV, build small and stay smallUS$m20.4
Mean NPV, build big nowUS$m16.1
Value of the options (decide later − stay small)US$m4.1
Value of waiting (decide later − build big now)US$m8.4
Chance the plant is expandedprobability31.6%
Chance the plant is soldprobability1.8%

How to read these results

  • On the business case, demand grows steadily and the large plant fills up: its NPV is far ahead. But demand is uncertain, and the large plant's extra capacity only pays when demand grows. Averaged over the possible futures its NPV is much lower, and the chance of losing money is high.
  • Starting small keeps the decision open. If demand is strong after two years, the company expands; if it collapses, it sells. The options turn part of the downside into upside: the staged strategy has the highest mean NPV.
  • The value of waiting is not free: expanding later costs more in total than building big at once, and two years of strong demand are lost to the small plant's capacity. The simulation weighs these costs against the protection.
  • The decision rules matter. Expanding at too low a demand level, or selling too readily, destroys the options' value: try other levels on the Inputs sheet and run again. The fan chart shows the two levels against the spread of demand.
  • On the business case, demand in year 2 is about 106 thousand units: between the two levels, so the plant carries on and neither option is used. The options exist only because demand is uncertain, which is why the business case cannot see their value.

See it move. Open the workbook, change an input on the Inputs sheet and run the simulation: every table and chart on this page updates in Excel.

Inputs and assumptions

Every assumption in the model, with its uncertainty and where it comes from. The figures are illustrative.

Market 4 inputs

Demand for the product and what each unit earns.

AssumptionUnitValue
Demand todayMarket study.thousand units / year100
Expected demand growthper year3.0%
Volatility of demandA new market: demand could double or halve within a few years.per year30%
Contribution per unitPrice less variable cost.US$ per unit300
Plants 8 inputs

The two plant sizes, the expansion and the sale.

AssumptionUnitValue
Large plant: capacitythousand units / year120
Large plant: investmentUS$m90
Large plant: fixed costsUS$m / year10.0
Small plant: capacitythousand units / year60
Small plant: investmentUS$m55
Small plant: fixed costsUS$m / year5.0
Expansion to the large plant's capacityPaid the year after the decision; the doubled plant has the large plant's fixed costs.US$m40
Sale of the small plantReceived at the end of the decision year.US$m35
Decision rules 3 inputs

Applied to the staged strategy at the end of the decision year.

AssumptionUnitValue
Decide at the end of yearAfter two years of sales; an expansion is ready the year after.year2
Expand if demand in the decision year is at leastthousand units120
Sell the plant if demand in the decision year is at mostthousand units40
Finance 1 input
AssumptionUnitValue
Discount rateCost of capital, real.per year9.0%

Units and conventions

Money
US$ million (US$m), today's prices; contribution in US$ per unit.
Demand
Thousand units a year.
Years
Year 0 is the investment; cash flows at the end of years 1 to 10.
Business case
The same calculation with demand growing exactly at its expected rate.

Key assumptions and limitations

Demand
Geometric Brownian motion: growth is persistent and the range widens every year.
Decisions
Taken once, at the end of year 2, on year-2 demand; the expansion is ready for year 3.
Plants
No residual value after year 10; fixed costs stop when the plant is sold.
Data
The company and all figures are invented for this example.

How to use it

  1. Enter your market, plant options and costs on the Inputs sheet.
  2. Press F9 on the Strategies sheet to watch the three strategies play out on the same demand.
  3. Run a simulation from the ModelRisk ribbon (10,000 samples with a fixed seed are set).
  4. Change the decision rules (the expansion and abandonment levels) and run again to find the best ones.

ModelRisk functions used

VoseTimeGBM
Ten years of demand: a growing, uncertain, persistent series.
VoseOutput
The NPV of each strategy, the decisions and the demand of every year as outputs.
VoseSimMean, VoseSimPercentile, VoseSimProbability
Statistics of the simulation for the tables and charts on the Results sheet.

Further reading

  • Monte Carlo simulation explained (Vose guide)
  • Dixit, A. K. & Pindyck, R. S. (1994). Investment under Uncertainty. Princeton University Press.
  • de Neufville, R. & Scholtes, S. (2011). Flexibility in Engineering Design. MIT Press.