ModelChoice decision tree · Oil and gas
Offshore Drilling Campaign Decision
Drill an exploration well now, shoot 3D seismic first, farm out the licence, or give it up?
From the model’s decision tree
Best first decision: Acquire 3D Seismic First
The expected value of each first option when every later decision is also made well (the tree rolled back).
| First decision | Expected value | |
|---|---|---|
| Drill Exploration Well | $34,300,000 | |
| Acquire 3D Seismic First | $40,000,000 | ✔ best |
| Farm Out (Keep 25%) | $12,612,500 | |
| Relinquish License | $0 |
| Measure | Value |
|---|---|
| Expected value of the best strategy | $40,000,000 |
| Chance of a loss on the best strategy | 71.0% |
| Best outcome on the best strategy | $347,000,000 |
| Worst outcome on the best strategy | −$53,000,000 |
S-curve (cumulative probability) of Acquire 3D Seismic First from the saved simulation.
The decision
An independent E&P company holds an exploration license in a deepwater block offshore West Africa. The license expires in 3 years, requiring a drilling commitment or relinquishment. The company must decide its exploration strategy.
Objective
Maximize expected NPV. This is the classic oil & gas exploration decision tree with geological risk, development cost uncertainty, and oil price risk.
The options
- Option 1: Drill Exploration Well ($45M)
Drill directly based on existing 2D seismic data. Five possible outcomes from major discovery (10%) to dry hole (30%). If discovery, decide: fast-track development, run appraisal wells, or sell the discovery.
- Option 2: Acquire 3D Seismic First ($8M)
Spend $8M on 3D seismic to de-risk the prospect before drilling. Better data improves well placement and raises discovery probability. Classic value of information decision.
- Option 3: Farm Out - Keep 25% ($2M)
Find a partner to drill in exchange for 75% working interest. Keeps exposure low but gives up most of the upside.
- Option 4: Relinquish License
Walk away. No further obligations.
The decision tree
The tree has 6 decisions, 14 chance events and 42 outcomes. The best path is open: at every decision the best choice is marked, and the expected value beside each branch counts every cash flow from the start. Open any other branch to see what follows it.
DecisionChance event+$ cash flow on the branch
Drill Exploration Well −$45,000,000expected $34,300,000
Chance: Exploration Well Result10% Major Discoveryexpected $353,000,000
Decision: Appraise Major DiscoveryFast-Track Development −$350,000,000expected $165,500,000
Chance: Fast-Track Outcome25% On Budget + High Reservesexpected $530,000,000
Chance: Oil Price (High Reserves)- 25% High Oil Price +$1,500,000,000payoff $1,105,000,000
- 50% Mid Oil Price +$900,000,000payoff $505,000,000
- 25% Low Oil Price +$400,000,000payoff $5,000,000
40% Over Budget + Good Reserves −$80,000,000expected $187,500,000
Chance: Oil Price (Good Reserves)- 25% High Oil Price +$1,100,000,000payoff $625,000,000
- 50% Mid Oil Price +$650,000,000payoff $175,000,000
- 25% Low Oil Price +$250,000,000payoff −$225,000,000
35% Major Cost Overrun −$150,000,000expected −$120,000,000
Chance: Oil Price (Cost Overrun)- 25% High Oil Price +$800,000,000payoff $255,000,000
- 50% Mid Oil Price +$400,000,000payoff −$145,000,000
- 25% Low Oil Price +$100,000,000payoff −$445,000,000
Appraisal Wells First −$60,000,000expected $353,000,000 ✔ best
Chance: Appraisal Results- 50% Confirms Large Field +$700,000,000payoff $595,000,000
- 35% Smaller Than Expected +$300,000,000payoff $195,000,000
- 15% Uneconomic at Current Price +$20,000,000payoff −$85,000,000
- Sell Discovery +$250,000,000payoff $205,000,000
15% Significant Findexpected $185,000,000
Decision: Appraise Significant FindDevelop (FPSO) −$200,000,000expected $110,000,000
Chance: Oil Price (Significant)- 25% High Oil Price +$600,000,000payoff $355,000,000
- 50% Mid Oil Price +$350,000,000payoff $105,000,000
- 25% Low Oil Price +$120,000,000payoff −$125,000,000
Appraisal Well −$40,000,000expected $185,000,000 ✔ best
Chance: Appraisal Result (Significant)- 40% Upgrades Estimate +$400,000,000payoff $315,000,000
- 40% Confirms Estimate +$250,000,000payoff $165,000,000
- 20% Downgrades +$50,000,000payoff −$35,000,000
- Sell Discovery +$100,000,000payoff $55,000,000
20% Marginal Findexpected −$20,000,000
Decision: Marginal Find OptionsTieback to Nearby Platform −$80,000,000expected −$28,500,000
Chance: Tieback Economics- 45% Profitable Tieback +$150,000,000payoff $25,000,000
- 30% Breakeven +$80,000,000payoff −$45,000,000
- 25% Uneconomic +$20,000,000payoff −$105,000,000
- Sell to Nearby Operator +$25,000,000payoff −$20,000,000 ✔ best
- Plug & Abandon −$5,000,000payoff −$50,000,000
- 25% Shows (Non-Commercial)payoff −$45,000,000
- 30% Dry Holepayoff −$45,000,000
Acquire 3D Seismic First −$8,000,000expected $40,000,000 ✔ best
Chance: 3D Seismic Interpretation30% Strong Prospectexpected $125,000,000
Decision: Drill Strong Prospect?Drill Well −$45,000,000expected $125,000,000 ✔ best
Chance: Well Result (Strong Prospect)- 40% Discovery +$400,000,000payoff $347,000,000
- 30% Marginal +$60,000,000payoff $7,000,000
- 30% Drypayoff −$53,000,000
- Farm Out with Data +$30,000,000payoff $22,000,000
40% Moderate Prospectexpected $10,000,000
Decision: Drill Moderate Prospect?Drill Well −$45,000,000expected $10,000,000 ✔ best
Chance: Well Result (Moderate)- 20% Discovery +$300,000,000payoff $247,000,000
- 30% Shows +$10,000,000payoff −$43,000,000
- 50% Drypayoff −$53,000,000
- Don't Drill +$5,000,000payoff −$3,000,000
- 30% Weak / No Prospect +$3,000,000payoff −$5,000,000
Farm Out (Keep 25%) −$2,000,000expected $12,612,500
Chance: Farm-Out Interest35% Major Operator Takes Itexpected $31,750,000
Chance: Major Operator Drills- 25% Discovery (Your 25%) +$120,000,000payoff $118,000,000
- 25% Marginal (Your 25%) +$15,000,000payoff $13,000,000
- 50% Dry Holepayoff −$2,000,000
- 35% Junior Operator +$8,000,000payoff $6,000,000
- 30% No Interestpayoff −$2,000,000
- Relinquish Licensepayoff $0
Change the numbers. Open the workbook with ModelChoice, change a probability or a cost in the tree, and the best decision updates at once.
Key assumptions
| Assumption | Value | Notes |
|---|---|---|
| Exploration Well Cost | $45,000,000 | Deepwater well, 60-90 day program |
| 3D Seismic Survey | $8,000,000 | 800 sq km, processing & interpretation |
| Fast-Track Development | $350,000,000 | FPSO + subsea, 3 year build |
| Appraisal Well Program | $60,000,000 | 2 appraisal wells + testing |
| Major Discovery Probability | 10% | 100+ MMbbl recoverable |
| Significant Find Probability | 15% | 30-100 MMbbl recoverable |
| Dry Hole Probability | 30% | No commercial hydrocarbons |
| Oil Price Scenarios | $50/70/100 bbl | Low/Mid/High, equal weighting |
| Major Discovery NPV (Mid) | $900M | At $70/bbl, fast-track development |
| Development Cost Overrun | 35-40% | Common in deepwater projects |
The figures are illustrative: the companies and numbers are invented for teaching.
Try it in ModelChoice
- Strategy Table. Compare drill-now vs seismic-first vs farm-out strategies
- Sensitivity Analysis. How does oil price and discovery probability affect EV?
- Risk Profile. Visualize the high-risk/high-reward nature of exploration
Find similar models
- Product
- Type
- Application
- Uses
Further reading
Download the workbook and open it with ModelChoice. The free trial opens every example.
Related example models
- ModelChoice★★★★★Mature Oil Field: Enhanced Oil Recovery DecisionFor a mature oil field: CO₂ injection, water alternating gas, a polymer pilot, primary recovery, or decommissioning?Three decisions and 11 chance events. Best first decision: Continue Primary Recovery, expected value $48.0m.
- ModelChoice★★★★★Refinery Upgrade DecisionAdd a coker, upgrade the hydrotreater, convert to biofuels, or sell the refinery as it is?One decision and 13 chance events. Best first decision: Full Coker Addition ($800M), expected value $795.6m.
- ModelChoice★★★★★LNG Export Terminal InvestmentBuild a full-scale LNG export terminal, a modular first phase, a floating unit, or nothing?Two decisions and ten chance events. Best first decision: Build Modular (Phase 1), expected value $1.32bn.
An illustrative example: the figures are invented for teaching. Last updated 9 October 2026.