Pharma R&D Portfolio: Which Projects to Fund | Vose Software

ModelRisk example · Pharmaceuticals and biotech

R&D Portfolio: Which Projects to Fund

Eight projects, one budget: which to fund for value, for a steady pipeline, and within the money we have?

  • Complexity: ★★★★★
  • Free Excel workbook (PH-04)
  • Needs ModelRisk: free trial

From the model’s saved run

Which portfolio?

Value (NPV, US$m), launches and budget risk of each candidate portfolio.

PortfolioMean NPVNPV 1 in 10 (P10)Launches expectedNo launch chanceOver budget chance
Everything (8 projects)540−4831.5915%100%
One per mechanism (5 projects)538−4371.3318%35%
Late stage (4 projects)513−4221.2520%35%
Within budget (4 projects)482−3161.0028%2%

Over budget: spending above US$170 million in at least one of the next 5 years.

Portfolio NPV — cumulative probability

The business question

A mid-sized pharma company has eight projects in development: a solid-tumour drug in Phase III, three projects in Phase II, two in Phase I and two in preclinical work.

Three pairs share a mechanism — two oncology projects act on the same apoptosis pathway, two immunology projects on the same interleukin, and two neurology projects on amyloid — so their Phase II results tend to agree. Each phase costs money, takes time and may fail. A project that fails stops spending.

The R&D budget is US$170 million a year for the next five years, and funding everything would need more in the early years. The portfolio committee is weighing four options: fund everything, fund one project per mechanism, fund only the late-stage projects, or fund a set that stays within the budget.

Who it is for
R&D portfolio committees, heads of development and strategy, finance teams in pharma and biotech.
Main outputs
For four candidate portfolios: NPV (mean and 1 in 10), expected launches, the chance of no launch, and the chance of breaking the budget · for each project: chance of launch, mean NPV, R&D cost and value per dollar · the effect of shared mechanisms · spending by year against the budget.

How the model works

Five sheets after this one, read from left to right. Each one feeds the next.

  1. Inputs sheet

    The annual R&D budget, the correlation between the Phase II results of projects that share a mechanism, the discount rate and the portfolio to chart.

  2. Projects sheet

    The duration and yearly cost of each phase. Each project's current stage, chance of success in each phase and value at launch (P10 and P90); which projects each portfolio funds.

  3. Pipeline sheet

    Three bivariate Normal copulas draw correlated uniforms for the Phase II results of each pair. VoseBernoulli decides every remaining phase. The last phase each project works on (its first failure, or the review), the year each phase would end and the launch year follow. The value at launch is discounted to today.

  4. Spend sheet

    The phase each project works on in each year — a Gantt chart of the iteration — gives its spending: the yearly cost of that phase. Each portfolio adds up the projects it funds. Its NPV, its launches, and whether it spends more than the budget in a year of the budget horizon.

  5. Results sheet

    The portfolios side by side; the projects ranked by value per dollar; how shared mechanisms make successes and failures come in pairs; spending against the budget.

ModelRisk techniques

  • Phase attrition VoseBernoulli
  • Correlated Phase II VoseCopulaBiNormal
  • Value at launch VoseLognormalAlt
  • Spending stops on failure
  • Four portfolios, same outcomes
  • Spending vs budget fan chart

Find similar models

Product

The results in detail

The projects

Each project as if funded: chance of launch, value and R&D cost (US$m).

Spending of the charted portfolio against the budget
ProjectStageLaunch chanceMean NPVR&D cost PV, meanValue per US$ of R&D
A ONC-301 solid tumoursPhase III53%4091593.58
B ONC-210 leukaemiaPhase II19%38911.41
C IMM-220 psoriasisPhase II19%22911.24
D IMM-110 Crohn's diseasePhase I13%3681.05
E NEU-120 Alzheimer's diseasePhase I8%26601.43
F NEU-010 Parkinson's diseasePreclinical5%3431.07
G RARE-230 enzyme deficiencyPhase II34%451121.40
H ONC-020 lymphomaPreclinical8%−4490.92

Value per US$ of R&D: the expected present value of the launch ÷ the expected R&D cost. Below 1, the project destroys value.

Shared mechanisms

Projects that share a mechanism succeed — and fail — together.

PairBoth launch simulatedBoth launch if independentRatio
B and H3.0%1.5%2.0
C and D5.0%2.5%2.0
E and F1.2%0.4%2.9

How to read these results

  • Funding everything gives the most value on average, about US$540 million, but it needs more than the US$170 million budget in the early years in every future: the Phase III drug and three Phase II projects all spend at once.
  • Funding one project per mechanism keeps almost all of that value, about US$538 million. The three projects it drops — D, F and H — are early and worth little on average: about a dollar of value per dollar of R&D. It still breaks the budget about one time in three, when several Phase II trials succeed and their Phase III trials start together.
  • The portfolio that stays within the budget (A, E, F and G) gives up about US$56 million of value, and its chance of no launch rises from 18% to 28%, because it leaves out two Phase II projects.

    The choice is between value and a steady flow of launches on one side and the budget on the other — unless more money is found, for example by partnering a Phase III.

  • Projects that share a mechanism succeed and fail together: each pair launches together two to three times as often as if they were independent. Funding both projects of a pair concentrates the risk, which is why funding everything has the worst 1-in-10 value of the four portfolios.
  • The Phase III drug, project A, carries every portfolio: most of the value and the reason the four NPV curves look alike. The portfolios differ in what happens if A fails — and in what they spend while waiting to find out.

See it move. Open the workbook, change an input on the Inputs sheet and run the simulation: every table and chart on this page updates in Excel.

Inputs and assumptions

Every assumption in the model, with its uncertainty and where it comes from. The figures are illustrative.

Budget and finance 4 inputs
AssumptionUnitValue
R&D budgetFor each year of the budget horizon below.US$m a year170
Budget horizonThe years the budget is set for.years5
Correlation of Phase II results within a mechanismOn the Normal scale: if the mechanism fails in one project, it probably fails in the other.copula ρ0.80
Discount rateper year10.0%
Chart 1 input
AssumptionUnitValue
Portfolio shown in the spending chart1 Everything · 2 One per mechanism · 3 Late stage · 4 Within budget.1 – 42

Units and conventions

Money
US$ million (US$m); costs discounted from the middle of each year, values from the launch year.
Time
Years from now; year 1 is the coming year.
Value at launch
The NPV, at launch, of the product's sales after all commercial costs.
Over budget
A portfolio's spending exceeds the budget in at least one year of the budget horizon (five years as shipped).

Key assumptions and limitations

Phases
Whole years, back to back; a project stops spending when a phase fails.
Correlation
Only through the Phase II results of projects sharing a mechanism; all other results are independent.
Unfunded projects
Shelved: no cost and no value. Partnering them out could recover some value.
Data
The company, the projects and all figures are invented for this example.

How to use it

  1. Enter your projects on the Projects sheet: stage, success rates by phase, value at launch.
  2. Mark which projects each candidate portfolio funds, and set the budget on the Inputs sheet.
  3. Run a simulation from the ModelRisk ribbon (10,000 samples with a fixed seed are set).
  4. Compare the portfolios on value, launches and budget risk; try other combinations.

ModelRisk functions used

VoseCopulaBiNormal
Correlated uniforms for the Phase II results of two projects sharing a mechanism (array).
VoseBernoulli
Whether each phase succeeds; the U argument takes the copula's uniform for Phase II.
VoseLognormalAlt
Each project's value at launch from its P10 and P90.
VoseOutput, VoseSimMean, VoseSimPercentile
Outputs and their statistics on the Results sheet.

Further reading

  • Monte Carlo simulation explained (Vose guide)
  • Paul, S. M. et al. (2010). How to improve R&D productivity: the pharmaceutical industry's grand challenge. Nature Reviews Drug Discovery 9, 203–214.
  • Vose, D. (2008). Risk Analysis: A Quantitative Guide, 3rd edition. Wiley.