Material Price Escalation and Procurement | Vose Software

ModelRisk example · Projects and construction

Material Price Escalation and Procurement Strategy

Buy the steel now, as needed, or with a price cap? Material escalation on a fixed-price contract.

  • Complexity: ★★★★★
  • Free Excel workbook (PC-07)
  • Needs ModelRisk: free trial

From the model’s saved run

Which steel strategy?

Total material cost (steel and concrete) under each strategy, on the same simulated prices (US$m).

StrategyMean US$mP90 US$mP99 US$mMean vs market, US$m
Buy at market prices as needed15.4618.0720.860.00
Forward contract for all the steel15.6715.9716.22+0.22
Forward contract for 50% of the steel15.5716.9018.32+0.11
Price cap on the steel15.5016.9317.29+0.04
Material cost — cumulative probability

The business question

The contractor has signed a fixed-price contract for a commercial building. The tender allowed US$900 a tonne for structural steel and a 3% escalation allowance on concrete. Steel is bought from month 4 to month 12, concrete from month 2 to month 17, and both prices can move a long way in that time — steel especially.

The steel supplier offers a forward contract at US$890 a tonne for the whole quantity. The bank offers a price cap at US$950 for a premium; or the contractor can buy as it goes and take the market price. Every option costs something: the forward price includes the supplier's carrying costs, the cap has a premium, and buying as needed carries the risk.

The model simulates monthly prices and applies the four strategies to the same price paths.

Who it is for
Contractors' commercial and procurement managers, estimators, and finance directors on fixed-price work.
Main outputs
Material cost under four steel strategies: mean, P90 and P99, the chance of staying within the tender allowance for all the materials and for the steel alone, and the cost of protection · the range of the steel price over the 18 months.

How the model works

Three sheets after this one, read from left to right. Each one feeds the next.

  1. Inputs sheet

    Quantities and the months in which they are bought. For steel and concrete, today's price, the expected annual escalation and the volatility; the forward price, the share bought forward in the partial option, the cap and its premium; the tender allowances.

  2. Purchases sheet

    VoseTimeGBM draws a monthly price path for each material, with drift set so that the expected price rises at the escalation rate. Steel bought in a month costs the month's price, the forward price, a blend, or the lower of the price and the cap plus the premium.

  3. Results sheet

    Total material cost under each strategy: its mean, high percentiles, how much more or less it costs on average than buying at market prices, and the chance of staying within the tender allowance — for all the materials, and for the steel alone, which is what the strategies change.

ModelRisk techniques

  • GBM with escalation VoseTimeGBM
  • Purchase profiles
  • Forward, partial forward, price cap
  • Price fan chart

Find similar models

Product

The results in detail

Within the allowances?

Concrete costs the same under every strategy, so the steel column shows what the choice of strategy changes.

StrategyAll materials within allowanceSteel alone within allowance
Buy at market prices as needed58.9%60.3%
Forward contract for all the steel62.7%100.0%
Forward contract for 50% of the steel60.2%62.6%
Price cap on the steel49.3%50.4%
MeasureUnitValue
Tender allowance for materialsUS$m15.74
…of which steelUS$m10.80

The steel price

The average price paid at market, and the monthly price range.

MeasureUnit10th pctMedian90th pctMean
Average steel price paid at marketUS$/t6778571,087872

How to read these results

Steel price by month — 10th to 90th percentile
  • Buying at market prices is cheapest on average when the offers include a margin, but it leaves the whole steel price risk: its P90 and P99 are the highest. A forward contract removes the steel risk at a small expected cost.
  • The cap protects against high prices and keeps the benefit of low ones. Its premium is paid on every tonne, so its mean is close to buying at market and its chance of staying within the allowance is the lowest — but steel can never cost more than the cap plus the premium, so its worst cases are bounded.
  • Even with all the steel bought forward, some risk remains: concrete escalation, which limits the chance for all the materials. The steel-alone column isolates the decision: as shipped, the forward contract keeps the steel within its allowance every time, the partial forward about 63% of the time, buying at market about 60% and the cap about 50%.
  • The fan chart shows why timing matters: the later the steel is bought, the wider the range of its price.

See it move. Open the workbook, change an input on the Inputs sheet and run the simulation: every table and chart on this page updates in Excel.

Inputs and assumptions

Every assumption in the model, with its uncertainty and where it comes from. The figures are illustrative.

Quantities and timing 6 inputs

What is bought, and in which months (evenly between the first and last month).

AssumptionUnitValue
Structural steelFrom the bill of quantities.tonnes12,000
Steel: first monthFrame erection starts in month 5.month4
Steel: last monthmonth12
ConcreteFoundations, slabs and cores.m³40,000
Concrete: first monthmonth2
Concrete: last monthmonth17
Steel price 3 inputs

Monthly geometric Brownian motion; the expected price grows at the escalation rate.

AssumptionUnitValue
Steel price todaySupplier's current list price for sections.US$/t850
Expected escalationConsensus forecast of construction-steel prices.per year4.0%
VolatilitySteel prices have moved this much in a typical year.per year25%
Concrete price 3 inputs

Less volatile, but escalates with labour and cement costs.

AssumptionUnitValue
Concrete price todayReady-mix supply agreement, indexed.US$/m³120
Expected escalationCement and haulage indices.per year5.0%
Volatilityper year6%
Steel procurement offers 4 inputs

Ways to buy the steel other than at market prices.

AssumptionUnitValue
Forward contract priceSupplier's offer for all deliveries; includes carrying costs.US$/t890
Share bought forward in the partial optionThe rest is bought at market prices.50%
Price capThe bank pays any excess of the market price over the cap.US$/t950
Cap premiumPaid on every tonne, whatever happens to the price.US$/t45
Tender allowances 3 inputs

What the fixed price assumed.

AssumptionUnitValueUncertainty
Steel allowanceUS$/t900Fixed
Concrete: escalation allowed in the tenderOn today's price.3.0%Fixed
Concrete allowanceToday's price plus the escalation allowed.US$/m³123.6Calculated

Units and conventions

Money
US$ million (US$m); prices in US$ per tonne of steel and per m³ of concrete.
Escalation
Expected annual price increase: the price model's drift is set so that the mean price grows at this rate.
Forward contract
A fixed price agreed now for delivery later.
Price cap
Pays the market price up to the cap, never more; costs a premium per tonne.

Key assumptions and limitations

Prices
Geometric Brownian motion with constant volatility; steel and concrete prices are independent.
Quantities
Quantities and purchase months are certain; no programme slippage (see PC-04).
Offers
No credit or delivery risk on the forward contract; storage is the supplier's.
Data
Prices, quantities and offers are invented for this example.

How to use it

  1. Enter your quantities, purchase months and the supplier's and bank's offers on the Inputs sheet.
  2. Set the escalation and volatility from price indices and the futures market.
  3. Run a simulation from the ModelRisk ribbon (10,000 samples with a fixed seed are set).
  4. Choose the strategy whose P90 (or P99) the business can live with, at an acceptable cost of protection.

ModelRisk functions used

VoseTimeGBM
Monthly steel and concrete price paths with escalation, as array formulas.
VoseOutput
Name the strategy totals and the monthly steel prices for the Results Viewer.
VoseSimMean, VoseSimPercentile, VoseSimProbability
Statistics of the simulation for the tables and charts on the Results sheet.

Further reading

  • Monte Carlo simulation explained (Vose guide)
  • AACE International (2008). Recommended Practice 58R-10: Escalation Estimating Principles and Methods Using Indices.
  • Hull, J. C. (2022). Options, Futures, and Other Derivatives, 11th edition. Pearson.