| Vose Software

Industry: Project Management
Product: ModelRisk
Application: Cost Estimation


From Class 5 to Class 1: Cost Estimation as a Shrinking Distribution

The AACE 18R-97 cost-estimate classification is explicit about what accuracy you are buying. A Class-5 concept estimate is −50% / +100% accurate at 80% confidence; a Class-1 definitive estimate is −10% / +15%. The numbers exist because EPC owners learned the hard way that a single dollar figure is meaningless without knowing the band around it. Yet most contractors still hand over a single number per class, with the band relegated to a footnote on the cover sheet.

A midstream gas-processing project — a $1.2B capital-investment decision — was estimated five times in ModelRisk, once per AACE class. The output at each gate was the same chart: a cumulative cost distribution with the P50 baseline and the P80 commit number marked. The point estimate stayed the cover-page headline; what the board approved was the P80 reading off the chart — and the value of front-end engineering became visible as the distribution physically tightening from one class to the next.

Cost estimate tightens as the project moves through AACE classes

Every curve passes through the same $1,200M point estimate at the P50, but the spread collapses as the estimate matures: the Class-5 concept curve is almost flat across a $600M-to-$2.4B band, while the Class-1 definitive curve is nearly vertical. The board does not commit to the point estimate — it commits to where each curve crosses the P80 line, and that reading marches from $1.89B at Class 5 down to $1.32B at Class 1.

Turning AACE accuracy bands into distributions

Each AACE class maps to a low/high accuracy percentage at 80% confidence. The simulation translates that band into a LogNormal whose P10 and P90 hit the class endpoints. LogNormal — not Normal — because:

  1. Cost is strictly positive.
  2. Construction-cost data is right-skewed at every WBS level (commodity spikes, scope creep, rework events all push up; nothing systematic pushes down).
  3. The published AACE bands are themselves asymmetric (Class 5 is −50% / +100%, not ±75%), which only a skewed distribution can honour.
AACE class Accuracy band P10 ($M) P50 ($M) P90 ($M)
Class 5 (concept) −50% / +100% 600 1,200 2,400
Class 4 (study) −30% / +50% 840 1,200 1,800
Class 3 (budget auth) −20% / +30% 960 1,200 1,560
Class 2 (control) −15% / +20% 1,020 1,200 1,440
Class 1 (definitive) −10% / +15% 1,080 1,200 1,380

The figures hold for any single point estimate of $1.2B; what varies as the project moves left-to-right on the AACE classes is the width of the distribution, not its centre.

Reading the opening chart more closely: at Class 5 the P80 sits at $1.89B — a 58% premium on the point estimate — and the curve is flat through a wide region, meaning the board cannot reasonably commit to any number narrower than that band. By Class 3 the P80 has tightened to $1.44B, and by Class 1 to $1.32B. The dollar value of progressing two classes is the difference between two P80s, which for this project was about $460M between Class 5 and Class 3 — easily justifying the front-end engineering spend that bought it.

Where the spread actually lives at Class 3

For the Class-3 budget-authorisation estimate, the WBS was rebuilt bottom-up — seven cost-component LogNormals plus three discrete risk-register events — and the full simulation was rerun.

Class-3 budget-authorisation estimate distribution

Class-3 P50 lands at $1.22B, P80 at $1.41B, P90 at $1.52B. The probability of breaching $1.5B is about 12% — the chart marks it directly. That number went straight into the board paper as "contingency is sized to hold the P80 at $1.41B, with a $50M strategic reserve lifting cover toward the P90."

Cost-component distributions — LogNormal across the WBS

What drives the spread

Tornado — Class-3 cost-estimate drivers

Mechanical equipment and bulk materials are the two largest drivers, near-tied at about ±$56M and ±$55M of half-spread, with direct field labour close behind at ±$41M — those three continuous WBS elements together dominate the at-completion spread. That ranking re-directed the Class-3-to-Class-2 engineering investment toward an equipment-package re-quote, MTO (material take-off) refinement and a labour-productivity study, rather than the lower-leverage line items. Discrete risk events rank below the top continuous drivers because their expected impact is folded into the central tendency; their spread contribution is smaller than the continuous-distribution width on the largest WBS elements.

What the model changed

  • The board approved against a P80 of $1.41B, not a $1.2B point estimate. The published authorisation was "$1.41B with a P50 expected outcome of $1.22B" — and the AACE accuracy claim was backed by a chart, not a footnote.
  • Class-progression spend was sized economically. The Class-3-to-Class-2 engineering work was budgeted at $14M because the simulation said it would narrow the P80 by about $40M of committed-but-undrawn contingency — a 2.8× return calculated before the work started.
  • Component-level contingency replaced blanket percentages. The 11% blended contingency was redistributed onto the high-spread WBS elements — mechanical equipment, bulks and direct labour — while engineering & PM, which the tornado showed was almost noise-free, was held near 8%.
  • The risk register became fundable. Three discrete events — scope creep, permitting drag, commodity squeeze — had expected costs above $5M apiece. Each got a named mitigation owner and a budget line.

ModelRisk functionality used

  • AACE-class-to-distribution mapping that translates the −50% / +100% style accuracy bands into fitted LogNormals whose P10/P90 match the class endpoints — the band becomes a distribution, not a footnote.
  • Bottom-up WBS rollup of seven cost-component LogNormals into a simulated total, with rank-correlation tornado isolating the largest individual driver.
  • Discrete risk-register integration with Bernoulli × LogNormal events summed into the WBS rollup.
  • Class-progression visualisation — the same simulation rerun at five accuracy bands, plotted as a single CDF set, so the narrowing of the distribution itself becomes the board's decision support.
  • P50 baseline and P80 commit-number outputs in the format the AACE TCM Framework calls for and that EPC owner organisations actually use in their stage-gate paperwork.
  • Rank-correlation driver ranking that re-prioritised the Class-3-to-Class-2 engineering investment toward the highest-spread WBS elements — mechanical equipment, bulk-material take-off and labour productivity.

The AACE estimate classes were never really about a number — they are about how confident you are entitled to be in that number. Monte Carlo simulation makes the entitlement explicit, and turns "Class 3, +30%/−20%" from a cover-sheet disclaimer into a curve the board reads off.