Industry: Transportation Product: ModelRisk Application: Signal-Timing Optimization at a Signalized Intersection
A US city ran the same 110-second fixed-cycle, 42-second green-split plan on a critical CBD-arterial intersection for nine years. The engineering team's deterministic Webster calculation, run once at the original 2015 design demand of 1,210 vph, said the plan was close to optimal. By 2024 the demand on the critical approach had drifted to a mean of 1,450 vph with a peak-extended-period mean of 1,711 vph, and the fixed plan was producing a mean per-vehicle delay of 131 seconds on the critical approach — past the LOS F threshold and tipping oversaturated on roughly half of all 15-minute intervals. The deterministic recalculation said "raise the cycle to 120 s." The simulation said the right answer is not a new fixed cycle. It is an adaptive Webster cycle that re-optimises every 15 minutes against the realised demand.
The clearest way to see the gap is to run both control schemes against the same simulated demand and compare the per-vehicle delay distributions. The fixed plan piles up against the LOS-F ceiling — mean 131 s/veh, with 51% of intervals above the 60-second LOS-E threshold. The adaptive Webster cycle pulls the whole distribution left to a mean of 62 s/veh and 25% above LOS E — a 53% cut in mean delay.
The team rebuilt the intersection model in ModelRisk: critical-approach flow is LogNormal, the green split is solved from the Webster formula
C* = (1.5 × L + 5) / (1 − Σy_i), with L = 12 s lost time/cycle
C* = (1.5 × L + 5) / (1 − Σy_i)
and per-vehicle delay is computed using the Webster delay equation with the actual degree of saturation x, not the design x.
Critical-approach flow on the corridor is LogNormal with mean 1,450 vph and CV 0.18. Saturation flow per lane is the HCM default 1,900 vph, applied to two through-lanes for 3,800 vph total saturation. Combining the critical-approach y = q/s with the other three phases' aggregate y (Triangular 0.32–0.58 reflecting cross-street empirical variability), the joint Y = Σy_i drives the Webster-optimal cycle, which spans an 82-to-180-second band across the day (mean 132 s):
A single fixed cycle at 110 s lives near the low end of optimal — too short for the heavy intervals, wrong every 15-minute interval. The Webster delay equation makes this worse: average delay is convex in x, so running x at 0.95 instead of 0.85 multiplies delay rather than nudging it up by 12%.
Running the two control schemes against the same simulated demand:
The adaptive scheme cuts mean per-vehicle delay by 53% and lifts realised throughput on the critical approach by 6%. The deterministic "longer cycle" fix would have moved the mean modestly — useful, but it cannot touch the P90 because it is still a single number facing a distribution.
The same adaptive controller delivers different throughput distributions across the day, and the simulation makes the dependence explicit:
Across the day the adaptive scheme serves demand right up to the saturation ceiling at each regime, where the single fixed 110-s plan leaves throughput on the table at both ends — too long for off-peak, too short for the peak.
The dominant driver is critical-approach mean flow (a 500 vph range moves mean delay ±14 s). Other-phase aggregate demand y (the Triangular 0.32–0.58) is second; it determines how much green the critical phase can claim. Saturation flow per lane is third — calibrating s up by 100 vph from the HCM default to a field-measured 2,000 vph shaved 9 s/veh from the simulated mean delay. Lost time per cycle matters more than expected: an 8-to-18 s range moves delay ±7 s/veh, and that was what justified replacing the 4-second amber/all-red intervals with 3-second intervals on a corridor with adequate stopping-sight distance.
A fixed-cycle plan optimises for an average rush hour that does not exist. ModelRisk gave the city the distribution that does — and 62 s/veh of average delay is what living inside that distribution looks like.