It depends on where your schedules live. If your planners work in Primavera P6 or Microsoft Project and you want a desktop tool that reads those schedules directly, checks them before modelling, updates in one click when the plan changes and has a published price, Tamara is the closest like-for-like replacement for Oracle Primavera Risk Analysis (PRA).
It is not the only option. This page covers what a replacement has to do, how to move a schedule risk model across without losing the thinking behind it, and what it costs. Our review of the wider category — Deltek Acumen Risk, Oracle Primavera Risk Analysis, Lumivero Schedule Risk Analysis, Intaver RiskyProject, Safran Risk and Tamara, each scored on usability, capability and price — is the top 6 project risk analysis tools.
A replacement has to do the whole quantitative schedule risk analysis (QSRA) job, not just put three-point ranges on durations: read the P6 schedule, check it is fit to simulate, model everyday uncertainty and discrete risk events separately, handle correlation, simulate cost with time, and report P-dates and drivers in a form management will read.
Use the checklist below on any tool you evaluate. The right-hand column is what Tamara does today.
A P80 date, for readers new to the term, is the finish date the project meets or beats in 80% of simulated outcomes. The gap between the deterministic date and the P80 date is the schedule contingency. The method behind all of this is set out in our guide to Primavera P6 schedule risk analysis.
Start from the schedule, not from the old risk model. Import the current P6 or Microsoft Project schedule into Tamara, fix what the health check flags, then rebuild uncertainty by work type, bring in the risk register, let shared factors carry the correlation, and run the result side by side with your last PRA analysis of the same schedule.
Tamara Desktop costs €2,150 per user per year, and a concurrent network seat costs €6,350 per year. Prices are published on our price list, with time and volume discounts on the price calculator, and there is a fully functional 15-day free trial.
For the prices other schedule risk tools publish, and how each scores on usability and capability, see the top 6 project risk analysis tools. When you compare, include the cost of the time your team spends rebuilding the model after each schedule update: a one-click update changes that number more than the licence price does.
Not necessarily, and that is worth knowing before you start. With the same schedule and the same inputs, two Monte Carlo tools should land close together. In practice the inputs change during a migration, because work-type uncertainty, factor-driven correlation and richer risk shapes replace task-by-task ranges, and those changes can move the P80 date, typically later if the old model left correlation out.
A later P80 is not a flaw in the new tool. It is usually the merge effect and correlation being priced in where the old model left them out, which is exactly what a schedule risk analysis is for. Running both side by side on one schedule, and tracing each difference to its cause, turns that conversation from “the new tool is pessimistic” into “this is the risk we were not seeing”.
Does Tamara change my Primavera P6 file? No. Tamara stores the risk model with a copy of the imported schedule in its own file and never modifies the original P6 or Microsoft Project file. When the plan is updated, one click re-imports it and the risk information is carried across.
Can Tamara handle very large schedules? Yes. Tamara has been tested on real project plans of up to 50,000 tasks. Typical schedules of 50 to 300 tasks return results in a fraction of a second, and 5,000 samples of a 34,000-task project run in under ten minutes.
Does Tamara work with Microsoft Project as well as P6? Yes. Tamara imports both Primavera P6 and Microsoft Project schedules, including nested and inter-connected projects, so a portfolio that mixes the two can be analysed with one tool.
Can I model costs and risks that are not in the schedule? Yes. Tamara includes a spreadsheet with the ModelRisk modelling tools, so costs, risks and calculations that live outside the master schedule, such as an NPV driven by the simulated finish date, sit in the same model.
Is there a free trial? Yes. The 15-day free trial is fully functional and imports your own P6 or Microsoft Project schedule, so you can run your first analysis on a project you are working on and compare it with your last result from your current tool.
Import your own Primavera P6 or Microsoft Project schedule, see its health check, and get P-dates, drivers and cost risk in one model, with a fully functional 15-day free trial.