Including identified risks in a project schedule model

MR-dice-icon.png Download a pdf copy of this help file  here

See also: Project risk analysis introduction, Project schedule risk analysis

The following example provides an illustration of how to include identified risks in a project schedule model:

A project consists of several activities as shown on the diagram below:

image86.gif

The duration of each activity is defined as a Triangle distribution with the minimum, most likely and maximum values.

Stages B, C and D can only start  after activity A is finished. Stages E, H and K can only start when all of B, C and D activities are finished. Stages N and O can only start when all of G, J and M activities are finished. Stage P can only start when both N and O activities are finished.

There are three risks that can influence the duration of certain stages as summarised below:

image87.gif

Each of these three risks influences just one stage (activity), however, this model can be extended so that one risk could affect the duration of any number of activities. The minimum, most likely and maximum values in the table above define the percentage of increase in duration of the affecting activity (for risk 1) and the additional number of weeks that the affecting activities will take if the risk occurs (for risks 2 and 3). The last column of the table above shows the probability of occurrence of each risk.

The task is to calculate the distribution for the total duration of the project.

The solution to this example is provided in the spreadsheet example model   Schedule model with risks.

See also: Quick calculation of total impact