One question that project managers will often ask is how the budget and
contingency set for the project as a whole should be distributed
back among the cost items to set budgets for each project component. This
knowledge will help the project manager to keep an eye on how the project
is progressing. Our approach is to distribute back the budget and contingency
costs so that the figures associated with each cost item have the same
probability of being exceeded.
Using this approach will give each cost item the same chance of coming
in within its budget figure or its (budget + contingency) figure and will
avoid controllers of some cost items being given almost impossible targets
to meet and others easy targets. This method of distributing budget and
contingency costs among cost items is demonstrated in the following example,
using this
cost model.
Example: Allocation of cost budget among cost components
The figure below shows the cumulative distribution of the project's total cost.

The mean of the generated values, £303 856 is selected as the budget and the (80 percentile - budget), i.e. £308 588 - £303 856= £4 732 is selected as the risk contingency. The budget is then the cost that the organization will realistically try to achieve or better, and the contingency is the additional amount put aside should the need arise. If the cost risk model is accurate, there is a 53% chance that the budget will be sufficient and an 80% chance that the project's costs will not exceed the budget + contingency.
In order to be able to distribute the budget and contingency back among the cost items, each cost item must be nominated as an output of the model. The generated data points from each cost item are then output to a spreadsheet and each column of values is then ranked separately in ascending order (see the figure below). Then, the costs generated for all items in each row are summed to give a total project cost.

Next, the budget and (budget + contingency) values are looked up in the column of summed costs and the values most precisely equating to the calculated budget and (budget + contingency) figures are determined. The values that appear in the same row for each cost item are then nominated as the budgets and (budget + contingency) values for the cost items. •